List of steps
(Total number of steps: 51)
Meet Hai Duong Department of Planning & Investment (DPI)  (2)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of foreign documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of Passport and/or Vietnamese ID cards  (2)
Obtain Functional Authorities's permission and Investment Certificate  (2)
Obtain authenticated copies of Investment Certificate.  (2)
Making seal  (2)
16
Make seal
Obtain Enterprise Registration Certificate (ERC)  (2)
Open bank account  (1)
Publish in newspaper  (1)
Obtain announcement on land measuring and setting up land recovery profile  (2)
Obtain Decision on approval of compensation and resettlement plan and land recovery  (5)
Pay compensation and support amounts  (1)
Obtain Decision on land recovery and land lease  (2)
Attend on-site title plan verification  (1)
Sign Land lease contract  (1)
Obtain Land use right Certificate and assets attached on land  (3)
Obtain approval of Environment Impact Assessment report (EIA)  (6)
Obtain approval of fire prevention and fighting  (3)
Obtain approval of detail construction planning (the Master site)  (3)
Obtain Construction permit  (3)

Preview & Print

Properties
 
33
Sign Land lease contract
(last modified: 6/20/2015)

Espera hasta paso siguiente

3 days  -  5 days

Contact details

Entity in charge

Hai Duong Department of Natural Resources and Environment

159 Ngo Quyen Street, Tan Binh District , Hai Duong
Tel: +84 3203 890 745
Website: http://tnmt.haiduong.gov.vn/

Unit in charge

Land Use Registration Division

Mon: 07:30-12:00, 13:00-16:30
Tue: 07:30-12:00, 13:00-16:30
Wed: 07:30-12:00, 13:00-16:30
Thu: 07:30-12:00, 13:00-16:30
Fri: 07:30-12:00, 13:00-16:30

Person in charge

Ms Nghiem Thi Thoa

Office staff
Tel: +84 3203 890 745, +84 987 975 250

Expected results

Signed Land Lease Contract Signed Land Lease Contract

Time frame

Waiting time until next step: Min. 3 days - Max. 5 days

Legal justification

1. Law on land No. 45/2013/QH13 dated 29/11/2013 of the National Assembly.
Law on land No. 45/2013/QH13 dated 29/11/2013 of the National Assembly.
Article 56
2. Decree No. 43/2014/ND-CP of the Government dated May 5, 2014 detailing the implementation of a number of articles of the Land on Land
Decree No. 43/2014/ND-CP of the Government dated May 5, 2014 detailing the implementation of a number of articles of the Land on Land
articles 14, 68.3

Additional information

After receiving "Decision on land lease price" from Hai Duong Department of Finance, Hai Duong Department of Natural resources and Environment will prepare "Land Lease Contract" and inform investor to come to sign the Contract. In this contract, investor can choose the form of payment: annual payment or one time payment for all land lease period.

After signing the contract, each parties will keep 01 original version for archives. Then the Department will has responsibility to prepare and send 1 full set of dossiers to Hai Duong Department of Tax for defining amount of land lease money investor needs to pay.

Recourse: Hai Duong Department of Natural Resources and Environment

Entity in charge

Hai Duong Department of Natural Resources and Environment

159 Ngo Quyen Street, Tan Binh District , Hai Duong
Tel: +84 3203 890 745
Website: http://tnmt.haiduong.gov.vn/

Unit in charge

One door Unit

Mon: 07:30-12:00, 13:00-16:30
Tue: 07:30-12:00, 13:00-16:30
Wed: 07:30-12:00, 13:00-16:30
Thu: 07:30-12:00, 13:00-16:30
Fri: 07:30-12:00, 13:00-16:30

Person in charge

Vu Hung Manh

Vice Chief of One door Unit
Tel: + 84 915 153 627
Email: manhtnmthd@gmail.com
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License