Requirements
Investor needs to submit to District People's Committee where the Land Plot is located below documents:
1.
Investment registration certificate (IRC) (Simple copy)
2.
Investment Project (Simple copy)
3.
Announcement on land measuring and setting up land recovery profile (original)
Time frame
Waiting time in queue:
Min. 10mn - Max. 15mn
Attention at counter:
Min. 10mn - Max. 15mn
Waiting time until next step:
Min. 30 days - Max. 45 days
Legal justification
1.
Law on land No. 45/2013/QH13 dated 29/11/2013 of the National Assembly.
articles 74, 75, 77, 80, 84
2.
Decree 47/2014/ND-CP dated 15/05/2014 by the Government promulgating regulations on compensation, support & resettlement as the State do recovery of land (Vietnamese version)
Article 28
3.
Circular No.37/2014/TT-BTNMT dated 30/6/2014 of Ministry of Natural Resources and Environment regulating on compensation, support and resettlement on Government's recovery of land (Vietnamese version)
Article 10
4.
Decision No.37/2014/QD-UBND dated 22/12/2014 of Hai Duong People's Committee promulgating regulations on compensation, support and resettlement as the State do recovery of land in Hai Duong province.
articles 26, 27
Additional information
After received "Announcement on land measuring and setting up land recovery profile" and dossiers from investor, District People's Committee will decide to set up "Compensation and Ground clearance Council", of which investor or investor's representative is a member.
The Compensation and Ground clearance Council will, in close cooperation with the investor (or investor's representative), prepare:
- Compensation, support and resettlement Plan (including name and address of person/household having recovered land; areas, types of land, location, original of land, number and quality of remain assets on land; basis for calculating compensations; amount money of compensation and support; plan for resettling, moving assets on land, grave etc)
- Obtain opinions of the owner(s) and user(s) of the project land plot and other related persons on the Plan .
- Finalize and submit the Plan to Hai Duong Department of Natural Resources and Environment for investigation.
* Document "Map of location, boundaries and areas of the recovered land plot for investment implementation" will be provided by District People's Committee. This land plot has already in the annual plan of using land of District and Province.