Invalid column name 'oldid'.
List of steps
(Total number of steps: 51)
Meet Hai Duong Department of Planning & Investment (DPI)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of foreign documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of Passport and/or Vietnamese ID cards  (2)
Obtain sectional cadastral map of the land plot estimated to lease  (2)
Obtain announcement of approval on investment intent and location  (4)
Obtain Investment Certificate  (1)
Obtain authenticated copies of Investment Certificate.  (2)
Obtain Enterprise Registration Certificate (ERC)  (2)
Making seal  (2)
21
Make seal
Open bank account  (1)
Publish in newspaper  (1)
Obtain announcement on land measuring and setting up land recovery profile  (2)
Obtain compensation, support and resettlement plan and related documents  (2)
Obtain Decision of approval on compensation, support and resettlement plan and land recovery  (2)
Pay compensation and support amount  (1)
Attend on-site title plan verification  (1)
Sign Land lease contract  (1)
Obtain Land use right Certificate and assets attached on land  (3)
Obtain approval of Environment Impact Assessment report (EIA)  (6)
Obtain approval of fire prevention and fighting  (3)
Obtain approval of detail construction planning (the Master site)  (3)
Obtain Construction permit  (3)

Preview & Print

Properties
 
11
Obtain sectional cadastral map of the land plot estimated to lease
(last modified: 6/24/2015)

Contact details

Entity in charge

Hai Duong Department of Natural Resources and Environment

159 Ngo Quyen Street, Tan Binh District , Hai Duong
Tel: +84 3203 890 745
Website: http://tnmt.haiduong.gov.vn/

Unit in charge

One door Unit

Mon: 07:30-12:00, 13:00-16:30
Tue: 07:30-12:00, 13:00-16:30
Wed: 07:30-12:00, 13:00-16:30
Thu: 07:30-12:00, 13:00-16:30
Fri: 07:30-12:00, 13:00-16:30

Person in charge

Ms Nghiem Thi Thoa

Office staff
Tel: +84 3203 890 745, +84 987 975 250

Expected results

Sectional cadastral map of the land plot 01 - Sectional cadastral map of the land plot

Requirements

1. Receipt of application for providing sectional cadastral map of investment location
Receipt of application for providing sectional cadastral map of investment location (original)

Time frame

Waiting time in queue: Min. 5mn - Max. 15mn
Attention at counter: Min. 5mn - Max. 15mn

Recourse: Hai Duong Department of Natural Resources and Environment

Entity in charge

Hai Duong Department of Natural Resources and Environment

159 Ngo Quyen Street, Tan Binh District , Hai Duong
Tel: +84 3203 890 745
Website: http://tnmt.haiduong.gov.vn/

Unit in charge

One door Unit

Mon: 07:30-12:00, 13:00-16:30
Tue: 07:30-12:00, 13:00-16:30
Wed: 07:30-12:00, 13:00-16:30
Thu: 07:30-12:00, 13:00-16:30
Fri: 07:30-12:00, 13:00-16:30

Person in charge

Vu Hung Manh

Vice Chief of One door Unit
Tel: + 84 915 153 627
Email: manhtnmthd@gmail.com
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License