List of steps
(Total number of steps: 45)
Meet Hai Duong Department of Planning & Investment (DPI)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of foreign documents  (3)
Obtain certified translation of documents  (2)
Sign the Land transfered Contract  (1)
Obtain authenticated copies of Passport and/or Vietnamese ID cards  (2)
Obtain announcement of approval on investment intent and location  (2)
Obtain Investment Certificate  (1)
Obtain authenticated copies of Investment Certificate.  (2)
Obtain Enterprise Registration Certificate (ERC)  (2)
Making seal  (2)
18
Make seal
Open bank account  (1)
Publish in newspaper  (1)
Obtain Decision on land recovery and lease  (2)
Complete financial responsibilities (if any)  (2)
Attend on-site title plan verification  (1)
Obtain Certificate of land use right and assets attached on land  (4)
Obtain fire prevention and fighting Certificate  (3)
Obtain Decision on approval of Environment Impact Assessment report (EIA)  (6)
Obtain Decision on approval of detail construction planning (the Master site)  (3)
Obtain Construction Permit  (3)

Preview & Print

Properties
 
28
Sign Land lease contract
(last modified: 6/17/2015)

Timeframe ( ver detalles )

Espera hasta paso siguiente

25 mn  -  45 mn
3 days  -  5 days

Contact details

Entity in charge

Hai Duong Department of Natural Resources and Environment

159 Ngo Quyen Street, Tan Binh District , Hai Duong
Tel: +84 3203 890 745
Website: http://tnmt.haiduong.gov.vn/

Unit in charge

Land Use Registration Division

Mon: 07:30-12:00, 13:00-16:30
Tue: 07:30-12:00, 13:00-16:30
Wed: 07:30-12:00, 13:00-16:30
Thu: 07:30-12:00, 13:00-16:30
Fri: 07:30-12:00, 13:00-16:30

Person in charge

Ms Nghiem Thi Thoa

Office staff
Tel: +84 3203 890 745, +84 987 975 250

Expected results

Signed Land Lease Contract Signed Land Lease Contract
Land lease payment notice Land lease payment notice

Time frame

Waiting time in queue: Min. 10mn - Max. 15mn
Attention at counter: Min. 15mn - Max. 30mn
Waiting time until next step: Min. 3 days - Max. 5 days

Legal justification

1. Law on land No. 45/2013/QH13 dated 29/11/2013 of the National Assembly.
Law on land No. 45/2013/QH13 dated 29/11/2013 of the National Assembly.
articles 122.2.b, 122.3.c
2. Decree No. 43/2014/ND-CP of the Government dated May 5, 2014 detailing the implementation of a number of articles of the Land on Land
Decree No. 43/2014/ND-CP of the Government dated May 5, 2014 detailing the implementation of a number of articles of the Land on Land
articles 30, 33, 125.3.c
3. Decision No.47/2009/QĐ-UBND dated 30/12/2009 regulating on authority, land withdraw, land lease orders, tranfer purpose of land use in the local.
Decision No.47/2009/QĐ-UBND dated 30/12/2009 regulating on authority, land withdraw, land lease orders, tranfer purpose of land use in the local.
articles 7, 8, 9

Additional information

After receiving "Decision on land lease price" from Hai Duong Department of Finance, Hai Duong Department of Natural resources and Environment will prepare "Land Lease Contract" and inform investor to come to sign the Contract.

After signing contract, each parties will keep 01 original version for archives. Then the Department will has responsibility to prepare and send 01 full set of dossiers to Hai Duong Department of Tax for defining amount of land lease money investor needs to pay.

Hai Duong Department of Tax will investigate dossier and issue "Land lease payment Notice within 03 to 05 working days, then the Department will send 01 version send to investor (usually by post), Department of Natural resources and Environment and other related authorities in the local.

Investor can directly collect "The Notice" at Administrative Unit - Hai Duong Department of Finance or at One Door Unit - Hai Duong Department of Natural resources and Environment.

Recourse: Hai Duong Department of Natural Resources and Environment

Entity in charge

Hai Duong Department of Natural Resources and Environment

159 Ngo Quyen Street, Tan Binh District , Hai Duong
Tel: +84 3203 890 745
Website: http://tnmt.haiduong.gov.vn/

Unit in charge

One door Unit

Mon: 07:30-12:00, 13:00-16:30
Tue: 07:30-12:00, 13:00-16:30
Wed: 07:30-12:00, 13:00-16:30
Thu: 07:30-12:00, 13:00-16:30
Fri: 07:30-12:00, 13:00-16:30

Person in charge

Vu Hung Manh

Vice Chief of One door Unit
Tel: + 84 915 153 627
Email: manhtnmthd@gmail.com
Powered by eRegulations (c), a content management system developed by UNCTAD's Investment and Enterprise Division, Business Facilitation Program and licensed under Creative Commons License