List of steps
(Total number of steps: 38)
Meet Hai Duong Industrial Zones Authority (IZA)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of foreign documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passport and/or Vietnamese ID cards  (2)
Sign MOU on land lease  (1)
Obtain Investment Certificate  (2)
Obtain authenticated copies of Investment Certificate.  (2)
Obtain Enterprise Registration Certificate (ERC)  (2)
Making seal  (2)
17
Make seal
Open bank account  (1)
Publish in newspaper  (1)
Sign official land lease Contract  (1)
Attend on-site title plan verification  (1)
Obtain Land Use Right Certificate  (2)
Obtain approval on Environment Impact Assessment (EIA)  (6)
Obtain fire prevention and fighting approval Certificate  (3)
Obtain written opinions on Conceptual plan  (3)
Obtain Construction Permit  (2)

Preview & Print

Properties
 
25
Prepare EIA report
(last modified: 6/16/2015)

Costs

( ver detalles )

Timeframe ( ver detalles )

Espera hasta paso siguiente

VND 15000000
20 mn  -  30 mn
30 days  -  45 days

Expected results

EIA report x7 01 - EIA report

Requirements

1. 01 - Libre deuda de patente
Investment Certificate (Inside IZs) (Simple copy)
2. 01 - Libre deuda de patente
Investment Project (Simple copy)
3. 01 - Libre deuda de patente
Sectional cadastral map of the land plot

Costs

Cost detail

Hypothesis

VND  15,000,000 per contract / transaction amount
- VND 15,000,000
Fee for making EIA report for reference only
1
The cost of preparing EIA report is for reference only and depends on each Consultant Company and aggreement between two parties. Normally in Hai Duong, the cost is about 15 million to 20 million VND.

Time frame

Waiting time in queue: Min. 10mn - Max. 15mn
Attention at counter: Min. 10mn - Max. 15mn
Waiting time until next step: Min. 30 days - Max. 45 days

Legal justification

1. Law No.52/2005/QH11 dated 29/11/2005 of National Assembly on Environment Protection (English version)
Law No.52/2005/QH11 dated 29/11/2005 of National Assembly on Environment Protection (English version)
articles 18, 19, 20
2. Decree No.80/2006/NĐ-CP dated 09/8/2006 of the Government regulating on implement some articles of Law on Environment.
Decree No.80/2006/NĐ-CP dated 09/8/2006 of the Government regulating on implement some articles of Law on Environment.
articles 8, 9
3. Decree No.29/2011/NĐ-CP dated 18/4/2011 of the Government regulating on Environment Impact Assessment Strategy, Environment Protection Commitment (English version)
Decree No.29/2011/NĐ-CP dated 18/4/2011 of the Government regulating on Environment Impact Assessment Strategy, Environment Protection Commitment (English version)
articles 12, 13, 14, 15, 16, 17
4. Circular No.26/2011/TT-BTNMT dated 18/7/2011 of Ministry of Natural Resources and Environment guiding on Environment Impact Assessment Strategy, Environment Protection Commitment.
Circular No.26/2011/TT-BTNMT dated 18/7/2011 of Ministry of Natural Resources and Environment guiding on Environment Impact Assessment Strategy, Environment Protection Commitment.
articles 10, 12

Additional information

For project which needs to carry out EIA report and obtains the appraisal of the report have been defined in the file attached below.

To make EIA report, investor should contact to any Consultancy company which has acquired legally-recognized function to prepare such report on investor's behalf.
List of projects required EIA report. List of projects required EIA report.