List of steps
(Total number of steps: 38)
Meet Hai Duong Industrial Zones Authority (IZA)
Obtain certified copies of foreign documents  (2)
Obtain consular legalized copies of foreign documents  (3)
Obtain certified translation of documents  (2)
Obtain authenticated copies of passport and/or Vietnamese ID cards  (2)
Sign MOU on land lease  (1)
Obtain Investment Certificate  (2)
Obtain authenticated copies of Investment Certificate.  (2)
Obtain Enterprise Registration Certificate (ERC)  (2)
Making seal  (2)
17
Make seal
Open bank account  (1)
Publish in newspaper  (1)
Sign official land lease Contract  (1)
Attend on-site title plan verification  (1)
Obtain Land Use Right Certificate  (2)
Obtain approval on Environment Impact Assessment (EIA)  (6)
Obtain fire prevention and fighting approval Certificate  (3)
Obtain written opinions on Conceptual plan  (3)
Obtain Construction Permit  (2)

Preview & Print

Properties
 
23
Submit application for Land use right Certificate
(last modified: 6/16/2015)

Timeframe ( ver detalles )

Espera hasta paso siguiente

10 mn  -  30 mn
5 days  -  7 days

Contact details

Entity in charge

Hai Duong Department of Natural Resources and Environment

159 Ngo Quyen Street, Tan Binh District , Hai Duong
Tel: +84 3203 890 745
Website: http://tnmt.haiduong.gov.vn/

Unit in charge

One door Unit

Mon: 07:30-12:00, 13:00-16:30
Tue: 07:30-12:00, 13:00-16:30
Wed: 07:30-12:00, 13:00-16:30
Thu: 07:30-12:00, 13:00-16:30
Fri: 07:30-12:00, 13:00-16:30

Person in charge

Ms Nghiem Thi Thoa

Office staff
Tel: +84 3203 890 745, +84 987 975 250

Expected results

Receipt of Land use right Certificate Application 01 - Receipt of Land use right Certificate Application

Requirements

Number of dossiers require to submit: 2 sets of dossier, includings:
1. Application for Land use right Certificate
Application for Land use right Certificate (original)
2. 01 - Libre deuda de patente
Authenticated copies of Investment Certificate
3. 01 - Libre deuda de patente
Signed official land lease Contract (IZs) (an authentic copy)
4. 01 - Libre deuda de patente
Minutes of Land Hand-Over (Simple copy)
5. 01 - Libre deuda de patente
Sectional cadastral map of the Land Plot (original)
(Industrial Zone Trading Company (lessor) has responsibility to provide this document to investor)

Time frame

Waiting time in queue: Min. 5mn - Max. 15mn
Attention at counter: Min. 5mn - Max. 15mn
Waiting time until next step: Min. 5 days - Max. 7 days

Legal justification

1. Law on land No. 45/2013/QH13 dated 29/11/2013 of the National Assembly.
Law on land No. 45/2013/QH13 dated 29/11/2013 of the National Assembly.
2. Decree No.43/2014/ND-CP dated 15/5/2014 of the Government regulating on implementation some articles of Law on land 2013
Decree No.43/2014/ND-CP dated 15/5/2014 of the Government regulating on implementation some articles of Law on land 2013

Recourse: Hai Duong Department of Natural Resources and Environment

Entity in charge

Hai Duong Department of Natural Resources and Environment

159 Ngo Quyen Street, Tan Binh District , Hai Duong
Tel: +84 3203 890 745
Website: http://tnmt.haiduong.gov.vn/

Unit in charge

One door Unit

Mon: 07:30-12:00, 13:00-16:30
Tue: 07:30-12:00, 13:00-16:30
Wed: 07:30-12:00, 13:00-16:30
Thu: 07:30-12:00, 13:00-16:30
Fri: 07:30-12:00, 13:00-16:30

Person in charge

Vu Hung Manh

Vice Chief of One door Unit
Tel: + 84 915 153 627
Email: manhtnmthd@gmail.com